Working at Height – Fall Arrest – How to Develop a Rescue Plan


Rescue Plan Guidance

Rescue plans don’t have to be complex.
Employers should implement a rescue plan that includes procedures for:
· Preventing prolonged suspension
· Performing rescue and treatment as quickly as possible
· Identifying orthostatic intolerance signs and symptoms

Management’s responsibility for safety needs to give careful consideration to the methodology of rescuing a fallen operative. Such considerations might include:

Dialing 999 - Often we think of the word ‘rescue’ as calling 999, but calling the local fire brigade does not constitute an effective rescue plan. Response times can be too slow, and not all fire brigades have the capability to rescue from height.

Crane Man Basket - This option has severe limitations, the main one being time. Target time from ‘Man Down’ to being recovered needs to be no more than five minutes. Other restrictions and shortcomings that make this a less than ideal solution are:

  • the crane is out of action for some reason, e.g. it may be ‘winded-off’;
  • the driver may be away from the crane; <
  • rescue by crane is limited to building façades and often is not able to provide access and rescue internal to the structure;
  • the crane man basket may be in the wrong location.
  • MEWP’s – This option for rescue can have its limitations such as available access and height restriction as the casualty may be at a height greater than the reach of the MEWP.

    Rope Access Rescue - Rope rescue requires a technical competency which demands a high level of training and re-training to acquire and retain this skill set. Given the limited time to complete a rescue, trained rope rescue personnel would need to be on stand-by and within close proximity to any incident. Donning the necessary kit to carry out a rope rescue can also be time consuming given that every minute the casualty is hanging is critical. Perhaps the greatest restriction is that it is a skill to which only a few would, or could, be trained.

    Third Party Rescue Systems - There are a number of considerations to take into account when considering third part rescue systems. In every consideration TIME is the critical factor. The speed with which the system can be deployed and the rescue carried out is vitally important, as is the SIMPLICITY and EASE of use so that a typical operative can deploy and carry out a rescue after being trained.
    Remember: whichever methodology you choose, the target time should be to rescue the casualty in under ten minutes.

    Planning for Fall Protection must include Rescue
    Having a rescue plan is just as important as having a fall protection plan. No site should have one without the other. Just putting together a fall protection program without rescue is only doing half the job.
    The onus is on the employer to ensure that the suspended operative is rescued quickly. That means ensuring that for anyone who works at height, there’s a rescue plan. Fall protection must include an emergency rescue plan.

    How will you rescue an operative who has fallen and is suspended in a fall-arrest system? Answering some basic questions can help in developing a rescue plan.

    Developing a Rescue Plan

    Rescue plan requires answers to the following questions

    If an operative’s fall is arrested can they be rescued in under five minutes?

    How will you know that someone has fallen?
    · Will someone see it happen?
    · Co-workers
    · Other trades
    · Plant personnel
    · Members of the public

    What communication systems will be used between the suspended operative and the rescue team?
    · How will the operative call for help?
    · Voice
    · Whistle
    · Mobile Phone

    Who will the Co-worker call?
    · Nearest co-workers
    · Supervisor
    · Site Management
    · 999 Fire /ambulance where available

    Is information available? Who and how will it be communicated?
    · Emergency phone numbers
    · Site address
    · Directions and access for ambulance/fire vehicle or other emergency services
    · Which floor/how high up
    · Operative’s condition after fall

    How will the safety of the rescuers be assured, as well as that of the suspended operative?
    · Are operatives trained and competent in the use of rescue equipment?
    · Is there sufficient number of trained personnel onsite?
    · Are rescue-training records kept up-to-date including any re-assessments?

    · Is the rescue equipment selected appropriate for the nature of the work?
    · What obstructions are in the way reaching the suspended operative?
    · Have assessments been made of anchor points?
    · Has consideration been given to the method of attaching to the casualty?

    How will rescue workers get to the casualty?
    · Rescue Ladder System
    · Rescue Haul System
    · Keys to building and roof
    · Elevator
    · Pull casualty in through window or balcony
    · Pull casualty up to floor/slab/roof
    · Climb/abseil down the building/structure
    · Aerial equipment from ground
    · Suspended access equipment
    · Crane Man Basket

    How will rescue be assured within five minutes of the occurrence of a fall to minimize the risk of further injury or death due to suspension trauma? And, what rescue equipment is needed?
    · Rescue Ladder
    · Rescue Haul System
    · Toxic shock strap
    · Suspended access equipment
    · Ropes
    · Aerial ladder truck
    · MEWPS or scissor lift
    · Climbing/rope rescue equipment
    · Crane Man Basket
    · First aid kit
    · Stretcher available should casualty be seriously injured

    What if the operative is injured?
    · Can the casualty still be rescued within five minutes?
    · Is there a qualified first-aider who understands suspension trauma and knows how to treat it?
    · Who and how will the emergency services and hospital be alerted?

    How will the public be protected?
    · Assign someone to direct traffic
    · Set up barriers

    How will the accident scene be protected?
    · Prevent further injury or damage
    · Set up barriers
    · Preserve wreckage
    · Aid investigation later

    Are there other considerations?
    · Working alone
    · Language barrier
    · Unusual features of building/structure
    · Wind
    · Other hazards
    · No emergency services nearby
    · Distance from rescue teams

    WARNING! An operative who has suffered a fall and is suspended in his harness is a true medical emergency. Just because they are hanging in a harness doesn’t mean you have all day to perform the rescue. Rescue has to be planned, practiced and performed quickly and effectively or the victim may very well die before the rescue finally occurs.

    “If you’re not going to give your employees the skills to perform rescue, then you might as well not even put them in the harness at all.”

    Practice can save lives

    Perhaps just as important as having a rescue plan in place is practicing the plan before a real-life fall occurs.

    Working at Height

    Safety at Height

    Working at Height Training

    Leading Edge

    Leading EdgeRescue at Height training courses have been designed with our extensive knowledge and experience of construction sites. We understand the operative capabilities, the scope of works involved in a project package and the constraints on access and restrictions and we have developed our training course accordingly.Being aware of the demands for fast, simple and effective rescue,when working at height Leading Edge Safety have developed a range of products and courses specifically designed for rescue at height in the construction industry, allowing typical site operatives to rescue conscious and unconscious casualties in under ten minutes.

    Popularity: 33% [?]

    Comments are closed.

    Guidance Podcasts
    Harness Articles
    At Height Training
    • HSE publications translated – Information and advice in world languages
      HSE welcomes people of all nationalities and ethnic backgrounds to its web site. If you are looking for information, help or guidance a number of publications have been translated into languages other than English. HSE publications translated – Information and advice in world languages […]
    • Quarry firm fined after worker plunge in 30-tonne wheel loader
      A quarry operator was today fined £30,000 after a 30-tonne wheel loader vehicle overturned and slid almost 16ft down a sand stockpile. Humberside Aggregates and Excavations Ltd, of Newport Road, North Cave, East Yorkshire, was also ordered to pay £10,590 in costs after pleading guilty to three separate breaches of Quarries Regulations 1999 in the prosecution […]
    • HSE targets ageing installations with new offshore inspection programme
      A new inspection programme of offshore oil and gas installations on the UK continental shelf is underway to ensure that ageing infrastructure does not adversely affect safety. After 40 years of oil and gas production in the UK sector of the North Sea, more than half of fixed platforms have exceeded their original design life or [...] […]
    • RR819: A small survey of exposure to rubber process dust, rubber fume and N-nitrosamines
      This report was carried out in support of HSE’s FIT3 Disease Reduction Programme Cancer Project’s aim to develop a strategy to reduce the incidence of occupational cancer in Great Britain. RR819 – A small survey of exposure to rubber process dust, rubber fume and N-nitrosamines […]
    • Workyear 2010/2011: Inspection of premises using MbOCA and isocyanates in the manufacture of moulded polyurethane articles
      This SIM provides guidance to inspectors on exposure to MbOCA and isocyanates in the manufacture of moulded polyurethane articles. View SIM 03/2010/07 – Workyear 2010/2011: Inspection of premises using MbOCA and isocyanates in the manufacture of moulded polyurethane articles […]
    • Buncefield prosecution – HSE podcast July 2010
      In this episode: We talk to HSE’s Deputy Chief Executive, Kevin Myers, about the prosecution of five companies held responsible for the explosion at Buncefield Oil Storage Depot in 2005. Buncefield prosecution – HSE podcast July 2010 […]
    • FAQs – Do employers have to provide personal protective equipment?
      The relevant regulations are the Personal Protective Equipment at Work Regulations 1992. Regulation 4 states: Every employer shall ensure that suitable personal protective equipment is provided to his employees who may be exposed to a risk to their health or safety while at work. Listen to HSE’s Infoline answer this question […]
    • Publication of HSE Annual Report and Accounts 2009/10
      The Annual Report reports on delivery of the HSE Business Plan 2009/10 together with other key developments in the organisation during the year. The Accounts include operating costs, recognised gains and losses, cash flows and a statement of financial position for HSE at 31 March 2010. View the HSE Annual Report and Accounts 2009/10 […]
    • Advice on acceptance criteria for damaged passive fire protection coatings on offshore installations
      This SPC introduces Offshore Information Sheet 12/2007, which provides guidance for evaluating the condition of passive fire protective coatings found offshore, and prioritising any repair action required. Feedback on issues raised as a result of inspections would be welcomed by OSD3.2. This SPC replaces SPC/Tech/OSD/36, which has been withdrawn. Advice on a […]
    • Riser emergency shut down valve (ESDV) leakage assessment
      This document describes how HSE assesses the acceptability of riser emergency shutdown valve (ESDV) leakage rates. This SPC replaces SPC/Tech/OSD/26 which has been withdrawn. Riser emergency shut down valve (ESDV) leakage assessment – view this document in full […]
    • Good and best practice offshore – collection of examples
      OSD need to identify and collect examples of good and best practice from regulatory interventions offshore. This SPC advises how this will be done. Good and best practice offshore – collection of examples view this document in full […]
    • Focus on…Serious accident on spindle moulder
      A worker making glazing beads on a spindle moulder received serious injuries to his hand, including amputations, when it went into the cutters as a result of a kickback. There was no false fence, tunnel guard or power feed fitted, so all the cutter block was exposed. The injuries were made much worse as ‘old style’ [...] […]
    • Operational circulars on REACH. OC 253/11, OC 253/12 and OC 253/13
      OC 253/11 – REACH (Registration, Evaluation, Authorisation and Restriction of Chemicals) – Guidance on the Regulation Read circular OC 253/11 OC 253/12 – Arrangements for the enforcement of REACH (Registration, Evaluation, Authorisation and Restriction of Chemicals) Read circular OC 253/12 OC 253/13 – Guidance on the interaction between COSHH and REACH ( […]
    • Worker loses lower leg after paving machine crush
      A Somerset construction firm has today been fined £10,000 after a worker’s foot was crushed under a paving machine – and he had to have his lower leg amputated. HSE prosecuted John Wainwright & Co Ltd for its role in the incident on School Road, Monkton in Heathfield on 29 August 2008. View press release ‘Worker loses [...] […]
    • Construction company put workers at risk of falls
      A major construction company has been fined today for failing to properly protect its workers from falls at height on a site in South Wales. Gee Construction Ltd was the principal contractor on the site at Castlegate, Caerphilly when a HSE inspector visited on 22 October 2009. View press release ‘Construction company put workers at risk of [...] […]
    • Castle Bromwich firm fined after worker injured by robot
      A Birmingham automotive firm has been fined after one of its employees was struck by a manufacturing robot, leaving his voice box damaged and almost paralysing him down one side of his body. HSE prosecuted Castle Bromwich-based Dura Automotive Body and Glass Systems UK yesterday (Wednesday) and the company was fined £30,000 and ordered to pay [...] […]
    • Noise ebulletin – free news and updates
      Subscribe today, receive a free email detailing the latest news and developments on the noise website. Latest ebulletin: Noise Podcast, HSE’s Pete Lennon talks about tackling the risks from noise and vibration in the workplace. Noise ebulletin – free news and updates […]
    • RR818 – Follow up evaluation of HSE’s web based Work-Related Violence Toolkit
      This project is the second phase of the evaluation of the ‘Managing violence in licensed and retail premises’ toolkit. The toolkit is aimed at duty holders in licensed and retail premises and is also intended as a resource for Local Authority inspectors. The HSE was interested in collecting feedback about the toolkit from people who had [...] […]
    • FAQs – When do the CDM Regulations 2007 apply to a project?
      The Construction, Design and Management (CDM) 2007 Regulations apply to most common building, civil engineering and engineering construction work. You must notify HSE of the site if the construction work is expected to either last longer than 30 days or involve more than 500 person days of construction work. Listen to HSE’s Infoline answer this question […]
    • HSE Chair’s speech at NEBOSH Graduation
      HSE Chair Judith Hackitt’s speech at the National Examination Board in Occupational Safety and Health graduation, 28 June 2010 View transcript of HSE Chair’s speech at NEBOSH Graduation […]